• We're proud to be the Navarre area's only independent professionally run Chamber of Commerce with an office located in the "Heart of Navarre" at 1804 Prado Street.  

    As we have for almost 50 years,

    we remain focused on our mission:

    "To promote civic and economic prosperity

    throughout our community."

  • INVEST IN NAVARRE!

    JOIN THE NAVARRE CHAMBER!

  • First replacement deck concrete pour completed for Pensacola Bay Bridge

    • Share:
    January 15, 2021
     
     
     
     
     
    For Immediate Release
    January 14, 2021
    Contact: Name Name:
    (850) 330-1205 | ian.satter@dot.state.fl.us
     
     
    First replacement deck concrete pour completed for Pensacola Bay Bridge
     
     
    TALLAHASSEE, Fla. Florida Department of Transportation (FDOT) contractors poured concrete for the first new bridge deck needed to repair the Pensacola Bay Bridge Wednesday, January 13. Bridge decks are the portion of the structure that connect two pier locations to form what is referred to as a bridge span.
     
    Repairing the bridge requires repair or replacement of eight full spans and 14 partial spans. Each full span is 150-feet long, 59-feet wide, and weighs approximately two million pounds. The Pensacola Bay Bridge has a targeted re-opening date of March 2021. Once repairs are complete, all four lanes will be open with no load restrictions.
     
    Details on the detour routes, including graphics, FAQs, and regular updates can be found online at fdot.gov/PensacolaBay. Members of the public wishing to receive these updates can choose to subscribe by providing their email address on this website as well.
     
    For additional real-time updates on the Pensacola Bay Bridge, follow FDOT District Three on social media: 
      ###
     
     
     
     
     
     
     
     
     
     