  • News Release: FDOT’s April 15 Updates on the Pensacola Bay Bridge Recovery Efforts

    • Share:
    April 15, 2021

    Florida Department of Transportation
    RON DESANTIS
    GOVERNOR
    605 Suwannee Street
    Tallahassee, FL  32399-0450
    KEVIN J. THIBAULT, P.E.
    SECRETARY
     
     
     
     
    For Immediate Release
    April 15, 2021
    Contact: Ian Satter
    ian.satter@dot.state.fl.us
     
    FDOT’s April 15 Updates on the Pensacola Bay Bridge Recovery Efforts
     
    PENSACOLA, Fla. As Florida Department of Transportation (FDOT) contractors install and repair the final five trophy pieces on the Pensacola Bay Bridge, considerable efforts have shifted to the construction and completion of the remaining bridge decks on the structure.
     
    Deck constructions consists of several key phases including:
    • Placement of concrete beams. During this process, precast beams are transported to the bridge site, and erected onto the abutments and piers.
    • Installation of stay-in-place forms and rebar (reinforced steel). The stay-in-place forms will allow the forms to remain in place when the concrete is poured, eliminating the need to remove the forms ultimately accelerating construction.
    • Pouring and leveling concrete. Concrete is poured in the forms and a machine levels and smoothes the concrete surface to ensure that the top of the slab is at the correct elevation or grade.
    • Curing of the deck. Curing keeps the concrete damp or moist until the hardening of concrete is complete, and strength is attained.
     
    The targeted reopening of the bridge remains the week of May 31, 2021. FDOT is regularly reviewing the contractor’s schedule of the entire Pensacola Bay Bridge Project with the anticipated completion date for all improvements currently scheduled for January 2022.
     
    Motorists should continue to use all available detour routes, which include the Garcon Point Bridge and State Road 87. At this time, tolls on the Garcon Point Bridge are suspended through Sunday, May 9, 2021. Commuters can also use the Escambia County Area Transit’s (ECAT) temporary bus route travel between Pensacola and Gulf Breeze free of charge.
     
    Details on the detour routes, including graphics, FAQs, and regular updates can be found online at fdot.gov/PensacolaBay. Members of the public wishing to receive these updates can choose to subscribe by providing their email address on this website as well.
     
    For additional real-time updates on the Pensacola Bay Bridge, follow FDOT District Three on social media: Twitter: @MyFDOT_NWFL and Facebook: @MyFDOTNWFL
    ###